19th December Painting | downloads: 348 | type: jpg | size: 717 kB |
| Painting started early in the building stage as we wanted a texture finished. When the building is near completion the final 3 coats of acrylic water base paint is applied. |
7th to 19th Tiling | downloads: 210 | type: jpg | size: 543 kB |
| Tiling takes a good week.When building with tilt panels be sure to wash the walls with tilt panel wash to remove the bond breaker or your tiles will fall off. Use a dark grout as a light colour will stain. |
1st December to 19th Concreting Driveways | downloads: 210 | type: jpg | size: 755 kB |
| December is very busy.We were lucky with the weather {No Rain} as it is the wet season here. |
23th to24th November 2007 Concreting Plant Room | downloads: 219 | type: jpg | size: 902 kB |
| Concreting of the plant room covers all the plumbing and electrical conduit. |
19th to 23 November 2007 Installing Electrical Conduts in Plant Room | downloads: 206 | type: jpg | size: 1 MB |
| Plant room Electrical looks very daunting, Anthony from Anthonys Electrical and Refrigeration Pty Ltd installed all the conduit including the security in 53 hours{On His own}.A great effort considering he has never done a car wash before. |
1st November to 24th Plumbing Installation | downloads: 203 | type: jpg | size: 974 kB |
| Plumbing is very busy. There is rainwater tanks to connect up as well as recycle and trade waste tanks. All recycle tanks had to be vented.Then there is drainage of the driveways and connection of the gross pollutant tank.The plant room piping is ready for concreting on 26th.The Boys from Mark Maunder Plumbing have produced excellent results. |
November 3rd to 9th Installing Structural Steel | downloads: 211 | type: jpg | size: 969 kB |
| The Steel installers were 3 days late but worked over the weekend to catch up. It is important the tilt panels are made to exact measurments so the steel can fit. |
25 October Tilt Panel Installation | downloads: 197 | type: jpg | size: 882 kB |
| Tilt panel installation only takes one full 12hour day which is good considering crane hire is $7.00 a minute. |
10th to 17th October 2007 Tilt Panel Construction | downloads: 220 | type: jpg | size: 1 MB |
| There are 23 tilt panels for our construction. First we need 4 level sites with a concrete base.When choosing the location of the slabs you have to consider access for the concrete trucks and crane placement when the panels have to be placed in position.Each day they pour 4 tilt panels starting with the biggest panels then using a Water base solution before each pour so the panels dont stick together. |
10th to 11th October 2007 "Installation water recycling tanks" | downloads: 263 | type: jpg | size: 1 MB |
| We are using 4 tanks for recycling.First the hole is dug to the required depth.Sand is placed on the bottom.The tanks are crained into position.Soil is compacted around the sides.Piping will be hooked up later.
The system when completed will recycle 3150 liters per hour
|